1 00:00:18,230 --> 00:00:15,829 Saturn five quarterly film report number 2 00:00:21,890 --> 00:00:18,240 three covers progress during the period 3 00:00:24,439 --> 00:00:21,900 May June July August 1963 highlighting 4 00:00:26,420 --> 00:00:24,449 major effort concentrated in initiation 5 00:00:34,760 --> 00:00:26,430 of fabrication of ground test stage 6 00:00:37,670 --> 00:00:34,770 components during this report period at 7 00:00:39,979 --> 00:00:37,680 Marshall s 1c efforts were primarily in 8 00:00:43,040 --> 00:00:39,989 support of the test fuel tank and the 9 00:00:44,959 --> 00:00:43,050 static test stage the s 1c test fuel 10 00:00:47,389 --> 00:00:44,969 tank schedule has been delayed more than 11 00:00:54,049 --> 00:00:47,399 12 weeks by late documentation releases 12 00:00:56,389 --> 00:00:54,059 and manufacturing problems among the 13 00:00:58,369 --> 00:00:56,399 first problems encountered was excessive 14 00:01:01,250 --> 00:00:58,379 thin out in hydraulically bulge formed 15 00:01:02,959 --> 00:01:01,260 bulkhead gore segments compensatory skin 16 00:01:05,810 --> 00:01:02,969 mill blanks will be used in alleviating 17 00:01:08,090 --> 00:01:05,820 thin out also clapping pressure will be 18 00:01:13,940 --> 00:01:08,100 controlled to permit drawing of metal 19 00:01:16,100 --> 00:01:13,950 from around the margins of the die early 20 00:01:17,780 --> 00:01:16,110 in this report period pressure spike 21 00:01:20,330 --> 00:01:17,790 problems were also encountered with 22 00:01:22,730 --> 00:01:20,340 explosive forming a technique used is 23 00:01:24,830 --> 00:01:22,740 back up to the Bulge forming method use 24 00:01:31,520 --> 00:01:24,840 of a neoprene blanket has alleviated the 25 00:01:34,010 --> 00:01:31,530 problem following chemical milling 26 00:01:36,080 --> 00:01:34,020 a-tryin manual rework of some gore 27 00:01:38,450 --> 00:01:36,090 segments was required because of a non 28 00:01:39,469 --> 00:01:38,460 uniform edge rate to relieve the 29 00:01:44,770 --> 00:01:39,479 thickness problem 30 00:01:49,969 --> 00:01:48,139 despite the earlier difficulties MSFC 31 00:01:52,310 --> 00:01:49,979 accomplished Meridian welding on the 32 00:01:54,889 --> 00:01:52,320 first bulkhead the upper bulkhead for 33 00:01:56,780 --> 00:01:54,899 the test fuel tank during May and the 34 00:02:03,499 --> 00:01:56,790 closure plate was welded into complete 35 00:02:05,810 --> 00:02:03,509 the first bulkhead after trimming the 36 00:02:07,880 --> 00:02:05,820 wiring mating edge of the first bulkhead 37 00:02:10,940 --> 00:02:07,890 was welded to the wiring in late May 38 00:02:13,400 --> 00:02:10,950 during girth welding porosity problems 39 00:02:13,970 --> 00:02:13,410 were encountered repairs were successful 40 00:02:16,520 --> 00:02:13,980 and the 41 00:02:18,380 --> 00:02:16,530 completed and accepted in August the 42 00:02:20,869 --> 00:02:18,390 porosity problem is being investigated 43 00:02:23,300 --> 00:02:20,879 several possible solutions are under 44 00:02:25,369 --> 00:02:23,310 study work is underway to complete a 45 00:02:34,070 --> 00:02:25,379 second bulkhead for use as the test 46 00:02:36,140 --> 00:02:34,080 tanks lower bulkhead in June 47 00:02:38,270 --> 00:02:36,150 Marshall finished welding on the upper 48 00:02:43,520 --> 00:02:38,280 cylindrical skin section for the test 49 00:02:45,559 --> 00:02:43,530 fuel tank during July the first 50 00:02:48,259 --> 00:02:45,569 cylindrical skin section was welded to 51 00:02:51,020 --> 00:02:48,269 the Y ring fabrication of a second skin 52 00:02:52,640 --> 00:02:51,030 section was begun with Marshall and the 53 00:02:54,500 --> 00:02:52,650 responsible contractor is now 54 00:02:57,289 --> 00:02:54,510 satisfactorily solving major 55 00:03:00,589 --> 00:02:57,299 manufacturing problems test fuel tank 56 00:03:04,190 --> 00:03:00,599 completion is forecast in December at 57 00:03:06,020 --> 00:03:04,200 Wichita fabrication of the s1 CT dual 58 00:03:09,020 --> 00:03:06,030 configuration thrust ring assembly 59 00:03:11,300 --> 00:03:09,030 fixture is underway however this and 60 00:03:13,130 --> 00:03:11,310 other items have been delayed because of 61 00:03:15,680 --> 00:03:13,140 late documentation releases and 62 00:03:20,809 --> 00:03:15,690 consequently delayed component tooling 63 00:03:23,300 --> 00:03:20,819 construction at Michou during program 64 00:03:25,879 --> 00:03:23,310 review in early August Marshall and 65 00:03:27,920 --> 00:03:25,889 Boeing formed a joint task group to deal 66 00:03:30,379 --> 00:03:27,930 with the s1 CT problems 67 00:03:32,390 --> 00:03:30,389 Marshall expects to reduce the present 68 00:03:38,539 --> 00:03:32,400 delay to 12 weeks during the production 69 00:03:40,690 --> 00:03:38,549 phase the thrust structure assembly 70 00:03:43,360 --> 00:03:40,700 fixture was completed at Wichita and 71 00:03:46,640 --> 00:03:43,370 installation begun at Marshall in August 72 00:03:49,370 --> 00:03:46,650 during August sufficient gore segments 73 00:03:51,500 --> 00:03:49,380 for the first test 1ct bulkhead plus 74 00:03:54,319 --> 00:03:51,510 spare segments were received at Marshall 75 00:03:56,629 --> 00:03:54,329 however bulkhead gore fittings are still 76 00:04:01,220 --> 00:03:56,639 in delay due to a change in forging 77 00:04:04,309 --> 00:04:01,230 requirements installation of two f1 78 00:04:05,780 --> 00:04:04,319 engine mock-ups on the s-1 sea basic 79 00:04:09,099 --> 00:04:05,790 thrust structure mock-up was 80 00:04:11,870 --> 00:04:09,109 accomplished at Marshall this quarter 81 00:04:13,699 --> 00:04:11,880 construction of the s-1 sea hydrostatic 82 00:04:16,490 --> 00:04:13,709 test and vertical Assembly Building at 83 00:04:18,529 --> 00:04:16,500 me Co is on schedule to meet the 84 00:04:21,379 --> 00:04:18,539 beneficial occupancy date of November 85 00:04:24,589 --> 00:04:21,389 first erection of structural steel is 86 00:04:27,350 --> 00:04:24,599 85% complete the west wall is being 87 00:04:32,110 --> 00:04:27,360 closed up and steel work on all others 88 00:04:38,119 --> 00:04:35,839 at Marshall's Mississippi test 89 00:04:40,219 --> 00:04:38,129 Operations construction is progressing 90 00:04:43,040 --> 00:04:40,229 on schedule completion of the dock and 91 00:04:44,629 --> 00:04:43,050 Road II is scheduled by November receipt 92 00:04:49,159 --> 00:04:44,639 of steel for the dock area was 93 00:04:50,600 --> 00:04:49,169 accomplished this quarter Harbor 94 00:04:54,050 --> 00:04:50,610 dredging is due to be finished by 95 00:04:55,339 --> 00:04:54,060 January 1964 contract award for the 96 00:05:00,019 --> 00:04:55,349 bascule bridge was made 97 00:05:01,850 --> 00:05:00,029 August 15 clearing of the static test 98 00:05:04,760 --> 00:05:01,860 area is scheduled for completion by 99 00:05:07,909 --> 00:05:04,770 December a contract was awarded in July 100 00:05:14,749 --> 00:05:07,919 for construction of the S 1 C and s 2 101 00:05:16,999 --> 00:05:14,759 stage test stand foundations a contract 102 00:05:20,119 --> 00:05:17,009 was awarded August 6th for assembly of 103 00:05:21,980 --> 00:05:20,129 2s1 C transporters assembly began 104 00:05:25,399 --> 00:05:21,990 immediately and is scheduled for 105 00:05:27,439 --> 00:05:25,409 completion by September 1964 the 106 00:05:29,779 --> 00:05:27,449 Marshall Center's hydrostatic test and 107 00:05:32,119 --> 00:05:29,789 vertical Assembly Building was inspected 108 00:05:34,459 --> 00:05:32,129 on August 15th and contractors are 109 00:05:36,950 --> 00:05:34,469 correcting deficiencies that official 110 00:05:39,490 --> 00:05:36,960 occupancy was granted and full-scale 111 00:05:42,439 --> 00:05:39,500 equipment installation is underway 112 00:05:44,809 --> 00:05:42,449 pouring of concrete for Marshalls s1c 113 00:05:47,029 --> 00:05:44,819 static test facilities towers was 114 00:05:49,640 --> 00:05:47,039 completed this quarter a direction of 115 00:05:51,649 --> 00:05:49,650 structural steel is underway on site 116 00:05:56,300 --> 00:05:51,659 deflector fabrication and installation 117 00:05:58,939 --> 00:05:56,310 of cable has also begun at Marshalls 118 00:06:01,550 --> 00:05:58,949 saturn v dynamic test facility area 119 00:06:03,399 --> 00:06:01,560 site preparation excavation for the 120 00:06:05,689 --> 00:06:03,409 tower base and pouring the foundation 121 00:06:07,820 --> 00:06:05,699 concrete were finished during the report 122 00:06:16,120 --> 00:06:07,830 period steel erection is scheduled to 123 00:06:22,280 --> 00:06:19,730 at Rocketdyne the use of ablative 124 00:06:24,290 --> 00:06:22,290 material in the f1 engine 16 to one 125 00:06:26,690 --> 00:06:24,300 nozzle extension was undertaken this 126 00:06:29,540 --> 00:06:26,700 quarter with initial short duration 127 00:06:32,210 --> 00:06:29,550 tests proving successful however during 128 00:06:35,380 --> 00:06:32,220 the third firing the liner bond system 129 00:06:38,030 --> 00:06:35,390 failed and ablative material was ejected 130 00:06:40,130 --> 00:06:38,040 investigation revealed that failure was 131 00:06:42,410 --> 00:06:40,140 due to poor bond between a bladed 132 00:06:47,330 --> 00:06:42,420 material and the structural honeycomb 133 00:06:49,550 --> 00:06:47,340 material a divergent ring baffled 134 00:06:52,010 --> 00:06:49,560 injector one of several designs 135 00:06:54,050 --> 00:06:52,020 undergoing tests is complete the 136 00:06:56,510 --> 00:06:54,060 injector consists of three radial 137 00:06:58,520 --> 00:06:56,520 baffles designed to aid indebting 138 00:07:01,220 --> 00:06:58,530 circumferential pressure oscillations 139 00:07:03,410 --> 00:07:01,230 and a divergent ring installed on the 140 00:07:05,420 --> 00:07:03,420 perimeter to help dampen chamber 141 00:07:07,700 --> 00:07:05,430 pressure waves near the injector face 142 00:07:13,130 --> 00:07:07,710 and protect the thrust chamber tubes 143 00:07:15,830 --> 00:07:13,140 adjacent to the injector crusher data 144 00:07:18,440 --> 00:07:15,840 from initial tests on the new f1 turbine 145 00:07:21,290 --> 00:07:18,450 exhaust manifold indicated unequal 146 00:07:23,180 --> 00:07:21,300 distribution of exhaust gases an angle 147 00:07:27,830 --> 00:07:23,190 baffle was inserted in the manifold 148 00:07:30,860 --> 00:07:27,840 Inlet to correct this condition at 149 00:07:33,740 --> 00:07:30,870 Edwards rocket site construction of new 150 00:07:37,040 --> 00:07:33,750 production f1 engine static test stands 151 00:07:39,200 --> 00:07:37,050 1c 1d and 1e continued with 152 00:07:41,360 --> 00:07:39,210 superstructure tanks and exhaust 153 00:07:44,600 --> 00:07:41,370 deflectors having been completed on 154 00:07:46,310 --> 00:07:44,610 stands 1d and 1e these stands will be 155 00:07:48,650 --> 00:07:46,320 complemented by the necessary block 156 00:07:52,340 --> 00:07:48,660 house and hangar facilities now also 157 00:07:55,070 --> 00:07:52,350 being built a new flame deflector has 158 00:07:57,410 --> 00:07:55,080 been installed in test stand one B at 159 00:07:59,720 --> 00:07:57,420 Edwards the installation was on an 160 00:08:04,850 --> 00:07:59,730 expedited basis to minimize interruption 161 00:08:07,670 --> 00:08:04,860 of testing on 1b construction of 162 00:08:10,490 --> 00:08:07,680 Marshalls f1 single engine static test 163 00:08:12,530 --> 00:08:10,500 stand is on schedule the concrete towers 164 00:08:19,390 --> 00:08:12,540 have been completed and steel erection 165 00:08:26,089 --> 00:08:23,629 at North American space and information 166 00:08:28,129 --> 00:08:26,099 systems division at Downey structural 167 00:08:30,320 --> 00:08:28,139 assembly of the s2 full-scale 168 00:08:33,680 --> 00:08:30,330 electromechanical mock-up was completed 169 00:08:36,250 --> 00:08:33,690 this quarter to j2 soft mock-up engines 170 00:08:39,829 --> 00:08:36,260 capable of gimbal have been installed 171 00:08:42,019 --> 00:08:39,839 mock-up completion is due in March 1964 172 00:08:44,360 --> 00:08:42,029 it will be used in establishing 173 00:08:46,490 --> 00:08:44,370 installation requirements and will 174 00:08:51,189 --> 00:08:46,500 provide s2 systems with checkout 175 00:08:56,360 --> 00:08:53,780 full-scale waffle sections for s2 176 00:08:58,819 --> 00:08:56,370 bulkheads have been machined for s and 177 00:09:05,150 --> 00:08:58,829 ID in preparation for high energy 178 00:09:07,129 --> 00:09:05,160 forming at El Toro initial proofing of 179 00:09:09,980 --> 00:09:07,139 methods and procedures for a chemical 180 00:09:12,350 --> 00:09:09,990 milling thin gore segments has also been 181 00:09:14,870 --> 00:09:12,360 accomplished at supplier facilities the 182 00:09:19,610 --> 00:09:14,880 thin segments are formed sized and heat 183 00:09:22,850 --> 00:09:19,620 aged prior to chem milling at SN ids 184 00:09:25,040 --> 00:09:22,860 tulsa plant s2 aft and forward skirt 185 00:09:26,750 --> 00:09:25,050 tooling has been completed and sub 186 00:09:29,300 --> 00:09:26,760 assembly of manufactured parts is 187 00:09:36,050 --> 00:09:29,310 underway the full-scale forward skirt 188 00:09:38,329 --> 00:09:36,060 mating jig is nearing completion parts 189 00:09:41,090 --> 00:09:38,339 for the s2 battleship thrust structure 190 00:09:42,710 --> 00:09:41,100 are being produced and inspected the 191 00:09:49,069 --> 00:09:42,720 structure is two months behind schedule 192 00:09:50,960 --> 00:09:49,079 because of manufacturing problems ground 193 00:09:54,680 --> 00:09:50,970 support equipment assembly has also 194 00:09:57,319 --> 00:09:54,690 begun at the tulsa facility installation 195 00:09:59,060 --> 00:09:57,329 of tooling @sn ids seal beach bulkhead 196 00:10:01,400 --> 00:09:59,070 fabrication building has been virtually 197 00:10:03,559 --> 00:10:01,410 completed tool proofing and 198 00:10:05,960 --> 00:10:03,569 certification have been accomplished on 199 00:10:08,240 --> 00:10:05,970 the bulkhead welders the common bulkhead 200 00:10:11,960 --> 00:10:08,250 automatic welding jig and the dollar 201 00:10:13,790 --> 00:10:11,970 section welder the autoclave lid and 202 00:10:19,280 --> 00:10:13,800 dome have been assembled and the 203 00:10:22,069 --> 00:10:19,290 honeycomb bonding tool completed sub 204 00:10:24,470 --> 00:10:22,079 assembly of the first s2 bulkhead for 205 00:10:27,439 --> 00:10:24,480 the structural test stage is underway 206 00:10:29,569 --> 00:10:27,449 the first thick to thin production gore 207 00:10:33,440 --> 00:10:29,579 segment weld was accomplished in late 208 00:10:43,410 --> 00:10:36,060 x-rays of the segment proved the wells 209 00:10:45,750 --> 00:10:43,420 to be satisfactory at the seal Beach 210 00:10:48,150 --> 00:10:45,760 hydrostatic test and vertical assembly 211 00:10:50,460 --> 00:10:48,160 facility the hydrostatic it's neared 212 00:10:52,020 --> 00:10:50,470 completion this quarter and tanks for 213 00:10:58,560 --> 00:10:52,030 the water conditioning facility were 214 00:11:01,950 --> 00:10:58,570 being fabricated at KOCO one Santa 215 00:11:04,170 --> 00:11:01,960 Susana the s2 battleship test stand all 216 00:11:06,390 --> 00:11:04,180 flame deflector anchors were placed on 217 00:11:08,730 --> 00:11:06,400 the completed foundation and all four 218 00:11:14,130 --> 00:11:08,740 retaining walls were erected early this 219 00:11:16,860 --> 00:11:14,140 quarter the battleship liquid oxygen 220 00:11:18,510 --> 00:11:16,870 tank was later installed and the service 221 00:11:20,910 --> 00:11:18,520 tower has been erected to the first 222 00:11:27,930 --> 00:11:20,920 level fabrication of the stages pro 223 00:11:31,440 --> 00:11:27,940 comment feed system is underway at koko 224 00:11:41,740 --> 00:11:31,450 for the all systems tests and all flame 225 00:11:46,960 --> 00:11:44,400 at Douglas Aircraft Santa Monica land 226 00:11:49,269 --> 00:11:46,970 fabrication and installation of s4b 227 00:11:50,100 --> 00:11:49,279 tooling is four to six weeks behind 228 00:11:52,600 --> 00:11:50,110 schedule 229 00:11:56,379 --> 00:11:52,610 pacing items included the LOX tank 230 00:11:59,530 --> 00:11:56,389 welder and common bulkhead tooling at 231 00:12:02,829 --> 00:11:59,540 Sacramento complex beta construction is 232 00:12:05,259 --> 00:12:02,839 continuing on schedule test stand beta 233 00:12:07,749 --> 00:12:05,269 one and three foundations are completed 234 00:12:11,050 --> 00:12:07,759 a direction of data one superstructure 235 00:12:15,100 --> 00:12:11,060 is underway work on the cryogenic 236 00:12:17,079 --> 00:12:15,110 vessels is in progress test stand data 237 00:12:20,079 --> 00:12:17,089 one instrumentation tunnel construction 238 00:12:22,929 --> 00:12:20,089 has been completed assembly of 239 00:12:25,449 --> 00:12:22,939 propellant tanks for the s4 V battleship 240 00:12:28,269 --> 00:12:25,459 stage was finished at complex beta 241 00:12:30,100 --> 00:12:28,279 during the report period hydrostatic 242 00:12:32,410 --> 00:12:30,110 test and calibration of the battleship 243 00:12:34,150 --> 00:12:32,420 stage tank was completed in late August 244 00:12:40,590 --> 00:12:34,160 as the next step 245 00:12:45,519 --> 00:12:43,210 construction of the s4 B Assembly 246 00:12:48,189 --> 00:12:45,529 Building at Douglass's Huntington Beach 247 00:12:50,920 --> 00:12:48,199 facility is continuing and tooling is 248 00:12:52,660 --> 00:12:50,930 being installed assembly tower 249 00:12:54,869 --> 00:12:52,670 foundations have been finished and 250 00:12:57,309 --> 00:12:54,879 structural steel is being erected 251 00:12:59,829 --> 00:12:57,319 construction is behind schedule however 252 00:13:02,230 --> 00:12:59,839 because of delays and contract award 253 00:13:05,100 --> 00:13:02,240 present estimated start of hydrostatic 254 00:13:08,170 --> 00:13:05,110 stage assembly is November 30th a 255 00:13:10,509 --> 00:13:08,180 full-scale mock-up of the s4 be forward 256 00:13:12,730 --> 00:13:10,519 dome and skirt section has been shipped 257 00:13:15,429 --> 00:13:12,740 from Douglas to the Marshall Center for 258 00:13:26,900 --> 00:13:15,439 use in evaluating interface problems and 259 00:13:32,330 --> 00:13:30,050 at Rocketdyne evaluation tests of an 260 00:13:35,180 --> 00:13:32,340 initial design of a pressurized armored 261 00:13:37,670 --> 00:13:35,190 harness for use on the j2 engine were 262 00:13:40,160 --> 00:13:37,680 held this quarter objective of the 263 00:13:42,080 --> 00:13:40,170 harness is to provide complete moisture 264 00:13:44,450 --> 00:13:42,090 abrasion and heat protection of 265 00:13:50,170 --> 00:13:44,460 electrical and fuel lines when the 266 00:13:55,760 --> 00:13:52,970 construction of j2 engine test stand 267 00:13:57,920 --> 00:13:55,770 Delta 2 at Santa Susana is almost 268 00:14:00,920 --> 00:13:57,930 complete the stand will initially be 269 00:14:10,550 --> 00:14:00,930 used to static fire the j2 in duration 270 00:14:12,500 --> 00:14:10,560 up to 500 seconds at sea level a two 271 00:14:15,920 --> 00:14:12,510 hundred twenty five foot tall exhaust 272 00:14:18,980 --> 00:14:15,930 stack at CTL five was installed to vent 273 00:14:25,820 --> 00:14:18,990 gases generated during j2 and f1 pump 274 00:14:28,880 --> 00:14:25,830 tests a prototype hyperflow system of 275 00:14:31,190 --> 00:14:28,890 generating steam was also tested steam 276 00:14:33,200 --> 00:14:31,200 is generated by injecting water into a 277 00:14:35,960 --> 00:14:33,210 heat generating device which operates 278 00:14:38,450 --> 00:14:35,970 like a rocket engine steam is ejected 279 00:14:40,880 --> 00:14:38,460 into a diffuser which lowers pressure in 280 00:14:43,370 --> 00:14:40,890 the altitude chamber to permit testing